Salt as energy storage: Vattenfall launch pilot project at heat plant in Berlin

Vattenfall, together with the Swedish company SaltX Technology, will test how renewable wind and solar power can be stored in salt. In experiments, SaltX's patented technology has proven to be able to store up to ten times more energy and for much longer periods than water. The technology will be tested for the first time on an industrial scale at a pilot plant in Vattenfall’s Reuter thermal power plant in Berlin.

The pilot plant at the Reuter thermal power plant in Spandau, Berlin, has a total storage capacity of 10 MWh and was officially commissioned today.

“In the next few months, we will collect important data to get answers to the question of whether and how this type of plant can be used in our business. Some questions are how large amounts of salt can be used, how quickly the storage medium reacts and how the process can be controlled,” said Markus Witt, responsible for the project at Vattenfall Wärme Berlin AG.

The patented technology developed by Swedish SaltX Technology is based on nano-coated salt. The technology enables this “salt battery” to be charged several thousand times and that the energy can be stored for weeks or months without losses.

“The energy sector is changing quickly, and we globally see an enormous need for energy storage. Germany is a country at the forefront of this development and we are proud to have Vattenfall as a partner. We are eager to launch our energy storage solution commercially as quickly as possible,” said Harald Bauer, CEO of SaltX Technology.

Test evaluation
The test operation at the plant in Berlin is planned to run until the end of the summer 2019. Thereafter, test data will be evaluated, and the results presented at the end of the year.

The pilot plant is part of a long-term rebuilding of the Reuter power plant. In 2019, Vattenfall will also start operating Europe's largest power-to-heat facility there, an energy store based on storage of hot water. During 2020, Vattenfall will take the Reuter C coal power plant out of service, which is a step in the plan to completely phase out all coal as a fuel in Vattenfall's heating operations in Berlin by 2030.

For more information, contact:
Vattenfall Press Office +46 8 739 5010, press@vattenfall.com

Attachments

See also

The Preem flag. Photographer: Preem

Vattenfall and Preem look into large-scale production of fossil-free hydrogen

The collaboration between Vattenfall and Swedish fuel company Preem, aimed at producing fossil-free hydrogen for biofuel production, is entering the next phase. A study is now being conducte...

Read the full article

Vattenfall and Kaunis Iron in a new partnership concerning electrified fossil-free mining operations

Vattenfall AB and Kaunis Iron AB have signed a letter of intent to develop fossil-free and electrified mining operations at the iron ore mine in Pajala.

Read the full article
Torbjörn Wahlborg, Senior Executive Vice President Generation at Vattenfall (left), and Kalev Kallemets, CEO of Fermi Energia, at signing of LOI at Vattenfall's headquarters in Solna, Sweden.

Vattenfall advances its Estonian cooperation on Small Modular Reactors

For the past year Vattenfall has participated in a feasibility study by the Estonian start-up energy company Fermi Energia to explore the possibilities for Small Modular Reactor (SMR) deploy...

Read the full article