Horns Rev 3 wind farm

Ørsted and Vattenfall link up offshore wind farms in the North Sea

A new eight-kilometre cable between Horns Rev 2 and Horns Rev 3 allows the two offshore wind farms to supply each other with electricity if the export connection to land is disconnected. The cable was used for the first time recently when the Danish system operator, Energinet, disconnected the export cable to Horns Rev 2 for four-days of scheduled maintenance work.

The owners of the two offshore wind farms, Ørsted and Vattenfall, invested in the 33 kV cable that creates additional security for the two energy companies’ billion-kroner investments in the North Sea. If there is a problem with the export connection to land, this is not only critical for the supply of electricity to customers on the mainland; it is also critical for the wind turbines.

“Offshore wind turbines must always be supplied with electricity; otherwise there is a risk of significant damage from for instance  humidity. The cable also enables a quick and easy start-up of the offshore wind farm once the export connection is back in service. In addition, we save a lot of diesel fuel and operating hours for the emergency generators for both the wind turbines and the service boats”, points out Niels Møller Jensen, Interface Manager at Horns Rev 3.

The cable, which was completed in April, is an optimal solution both in terms of the environment and with regard to investments and operating costs. It was used for the first time recently when Energinet had to disconnect the export cable from Horns Rev 2 for four days for maintenance works. During this time, the wind farm was supplied with electricity from Horns Rev 3.

“We are really happy that we could supply our 91 wind turbines with back-up electricity from Horns Rev 3 during Energinet’s planned inspection of the export cable’s high voltage switch. Thanks to the new cable, we were able to resume generation of renewable power much faster”, says Allan Due Overbeck, Head of Operations Horns Rev 2.

The wind turbines at Horns Rev 2 normally get emergency power from a central generator on an offshore platform. At Horns Rev 3, each turbine has a small emergency generator.

This is the first time the two offshore wind farms, which have different owners, have backed each other up in this way. Horns Rev 2 has been in operation since 2009, while Horns Rev 3 first began supplying power to the electricity grid in December and will be operating at full capacity by the end of the summer.

See also

Vattenfall and BASF award key contracts for Nordlicht offshore wind projects

Suppliers for key components and installation services are under contract

Read the full article
Louis Dreyfus Armateurs service operation vessels

Vattenfall signs contract for wind farm service vessels

Vattenfall has signed a contract with French ship owner Louis Dreyfus Armateurs for up to three large Service Operation Vessels to be used at existing and planned offshore wind farms in the ...

Read the full article

Finland’s first commercial-scale offshore wind farm underway

The work is already in full swing in Korsnäs off the west coast of Finland where one of the most significant industrial projects in the country is in progress. To achieve carbon neutral...

Read the full article