Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection

Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the construction of an offshore grid connection for the Hollandse Kust Zuid I and II wind farms. The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform.

Vattenfall won this first subsidy free public tender issued by the Dutch government in March 2018.

Marco Kuijpers, Senior Manager Offshore Nederland at TenneT: ‘This agreement is another fantastic step towards making the Dutch electricity system sustainable. The sea grid is now really taking shape, first with 1,400 MW in the Borssele wind area, followed by Hollandse Kust Zuid and finally Hollandse Kust Noord in 2023. In the meantime, we’re preparing for the next North Sea projects in consultation with the Ministry of Economic Affairs & Climate.’

'This is a big milestone for the project and we’re glad that it is advancing well’, says Gunnar Groebler, Head of BU Wind and member of the EGM of Vattenfall. Contracts are signed well ahead of the deadline in March this year. We are looking forward to continue our cooperation with TenneT and materialize this project as a big contribution to the Dutch energy transition.’

Offshore grid: Hollandse Kust Zuid

Hollandse Kust Zuid offshore grid comprises two transformer platforms at sea, each with a 700 megawatt capacity, two 220 kV alternating current cables per platform, a yet-to-be-constructed onshore substation and an expansion of the existing ‘De Maasvlakte’ onshore high voltage substation where wind power from the sea is connected to TenneT’s Randstad 380 kV Zuidring. The wind power will be supplied to electricity consumers across the country via the national high voltage grid.

TenneT’s offshore transformer platform (artist’s impression).jpg

TenneT’s offshore transformer platform (artist’s impression)

TenneT has been officially designated by the Dutch government as offshore grid operator. TenneT is realising grid connections at sea with a total capacity of at least 3,500 MW, in accordance with a standardised concept of 700 MW per grid connection. The two connections from the Hollandse Kust Zuid offshore grid, which have a joint capacity of 1,400 MW, will become operational a year apart, in 2021 and 2022, in accordance with the Energy Agreement.

Facts and figures about Hollandse Kust Zuid I and II

  • 356 km2 in total, 22.2 km from the Dutch west coast
  • Total capacity: 700 - 750 MW
  • Sustainable electricity for 1 to 1.5 million households

See also

Transition pieces for wind turbines. Photo: CS Wind.

First components for Nordlicht I completed ahead of schedule

The Nordlicht cluster has reached an important milestone before offshore construction is set to begin later this year: the first monopiles and transition pieces for Nordlicht I have been suc...

Read the full article
A remotely operated vessel.

World War II sea mines removed from wind farm site

Sometimes the path to clean energy starts with a look into the past. Last year, the Nordlicht project's geoscience team completed a special campaign: to remove mines from the Second World Wa...

Read the full article
Drone view of Prinses Ariane wind farm on a winter's day.

Flexibility: wind power increasingly important for a stable electricity system

Technological developments are challenging old perceptions of wind power generation. Today, wind power is becoming increasingly important in delivering ancillary services that stabilise the ...

Read the full article