Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection

Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the construction of an offshore grid connection for the Hollandse Kust Zuid I and II wind farms. The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform.

Vattenfall won this first subsidy free public tender issued by the Dutch government in March 2018.

Marco Kuijpers, Senior Manager Offshore Nederland at TenneT: ‘This agreement is another fantastic step towards making the Dutch electricity system sustainable. The sea grid is now really taking shape, first with 1,400 MW in the Borssele wind area, followed by Hollandse Kust Zuid and finally Hollandse Kust Noord in 2023. In the meantime, we’re preparing for the next North Sea projects in consultation with the Ministry of Economic Affairs & Climate.’

'This is a big milestone for the project and we’re glad that it is advancing well’, says Gunnar Groebler, Head of BU Wind and member of the EGM of Vattenfall. Contracts are signed well ahead of the deadline in March this year. We are looking forward to continue our cooperation with TenneT and materialize this project as a big contribution to the Dutch energy transition.’

Offshore grid: Hollandse Kust Zuid

Hollandse Kust Zuid offshore grid comprises two transformer platforms at sea, each with a 700 megawatt capacity, two 220 kV alternating current cables per platform, a yet-to-be-constructed onshore substation and an expansion of the existing ‘De Maasvlakte’ onshore high voltage substation where wind power from the sea is connected to TenneT’s Randstad 380 kV Zuidring. The wind power will be supplied to electricity consumers across the country via the national high voltage grid.

TenneT’s offshore transformer platform (artist’s impression).jpg

TenneT’s offshore transformer platform (artist’s impression)

TenneT has been officially designated by the Dutch government as offshore grid operator. TenneT is realising grid connections at sea with a total capacity of at least 3,500 MW, in accordance with a standardised concept of 700 MW per grid connection. The two connections from the Hollandse Kust Zuid offshore grid, which have a joint capacity of 1,400 MW, will become operational a year apart, in 2021 and 2022, in accordance with the Energy Agreement.

Facts and figures about Hollandse Kust Zuid I and II

  • 356 km2 in total, 22.2 km from the Dutch west coast
  • Total capacity: 700 - 750 MW
  • Sustainable electricity for 1 to 1.5 million households

See also

Bruzaholm´s wind turbines are arriving

The installation of 21 wind turbines in Bruzaholm has now begun. This involves, among other things, transporting the 83-metre-long turbine blades by special transport on the roads of souther...

Read the full article
Seaweed farming

From the Baltic to the North Sea: Expanding WIN@sea Brings Seaweed Farming Closer to Local Fishermen

After successfully testing multi-use offshore practices at Danish Kriegers Flak in the Baltic Sea, Vattenfall and its project partners are now bringing the pioneering WIN@sea project to the ...

Read the full article
Construction work at Bruzaholm wind farm in Sweden

Teaming up for net zero: collaboration cuts carbon at Bruzaholm wind farm

When Swedish Bruzaholm wind farm is completed this autumn it will not only produce fossil free power. It will also be a shining example of how partnering can spur innovative ideas.

Read the full article