On Friday, the 72nd and last foundation for Kriegers Flak Offshore Wind Farm was successfully placed in the Baltic Sea.

All Kriegers Flak foundations installed

On Friday, the 72nd and last foundation for Kriegers Flak Offshore Wind Farm was successfully placed in the Baltic Sea.

Although working under special circumstances due to Covid19, the installation of the foundations, which started in May, were completed on schedule in a little over three months.

Once completed, Kriegers Flak will be Denmark’s largest offshore wind farm with a capacity to cover the annual electricity consumption of approximately 600,000 Danish households.

Next major step in the project will be the installation of cables and turbines. Cable installation and testing is scheduled to be completed in November this year, and the turbine installation is expected to start in early 2021. This puts the wind farm on schedule to be in full operation by the end of same year.

Kriegers Flak is the latest and largest of Vattenfall’s recent offshore projects in Denmark. The others being Horns Rev 3, which was inaugurated last year, and Vesterhav Syd & Nord, which are scheduled to be in full operation by the end of 2023, at latest.

About Kriegers Flak Offshore Wind Farm

  • With a production capacity of just over 600 MW, Kriegers Flak will be Denmark’s largest offshore wind farm.
  • The offshore wind farm’s production can cover the annual electricity consumption in 600,000 Danish households.
  • The 72 turbines have a total height of 188 metres and each monopile foundation weighs up to 800 tonnes.
  • The wind farm is located in the Baltic Sea, 15-40 kilometres off the Danish coast.

See also

Aerial view of a rural construction site with a tall yellow tower crane, construction vehicles and temporary buildings, surrounded by fields, woodland, and rolling hills in the background.

Vattenfall builds combined wind and solar park in south-west Germany

Hybrid park Hommerdingen-Biesdorf is Vattenfall’s first combination of wind and PV in Germany and sets standards for modern, cost-efficient, and grid-friendly energy generation.

Read the full article
Transition pieces for wind turbines. Photo: CS Wind.

First components for Nordlicht I completed ahead of schedule

The Nordlicht cluster has reached an important milestone before offshore construction is set to begin later this year: the first monopiles and transition pieces for Nordlicht I have been suc...

Read the full article
A remotely operated vessel.

World War II sea mines removed from wind farm site

Sometimes the path to clean energy starts with a look into the past. Last year, the Nordlicht project's geoscience team completed a special campaign: to remove mines from the Second World Wa...

Read the full article