Installing first turbine at Kriegers Flak

First turbine at Kriegers Flak offshore wind farm in place

The first turbine at the Kriegers Flak offshore wind farm is in place and will deliver the first fossil-free electricity shortly. It will be the largest offshore wind farm in Denmark.

On 27 January, the tower, nacelle and blades were installed for the first turbine at the Kriegers Flak offshore wind farm in the Baltic Sea. A process that normally takes about 14 hours.

"We are proud that the first of many turbines at Kriegers Flak is now in place and ready to produce electricity. We expect that households and industry one of the coming days will receive the first fossil-free electricity from the turbine. It is an important milestone in the project, it is happening on schedule and it is fantastic to see the offshore wind farm take shape,” says Jacob Nørgaard Andersen, Country Manager at Vattenfall Denmark.

The installation follows the granting last week by the Danish Energy Agency of the license to produce electricity. Despite the restrictions caused by the COVID-19 pandemic, the construction of Kriegers Flak is generally proceeding according to plan and scheduled to be fully operational by the end of 2021, at the latest.

“Kriegers Flak makes a significant contribution in the Nordic region to our goal of enabling fossil-free living. It is a unique project integrating offshore wind production and interconnectivity between two countries – Denmark and Germany. And at the same time, it signals that the exploitation of the Baltic Sea's huge potential for offshore wind is now gaining momentum,” says Catrin Jung, Head of Offshore Wind in Vattenfall.

Compared to 2019, Kriegers Flak will increase the Danish production of wind energy by 16 per cent or enough to cover the annual electricity consumption of approximately 600,000 Danish households.

The individual parts of the turbines are assembled at Port of Roenne on the Danish island of Bornholm. Afterwards they are shipped in sets of four to the construction site at sea. The 72 turbines are produced by Siemens Gamesa Renewable Energy and will be commissioned on an ongoing basis as they are installed.

Vattenfall is Denmark's largest developer of offshore wind and is, in addition to Kriegers Flak, also building two offshore wind farms off Jutland's west coast.

Facts about Kriegers Flak

  • Kriegers Flak will have a production capacity of around 600 MW.
  • Approximately 600,000 Danish households can have their annual electricity consumption covered by the offshore wind farm.
  • Each of the 72 wind turbines is 188 metres tall, and each foundation weighs up to 800 tonnes.
  • The offshore wind farm is located in the Baltic Sea, 15-40 kilometres off the Danish coast.
  • The site covers an area of 132 km2 and has approximately 170 kilometres of subsea cables.
  • The farm is expected to be fully operational by the end of 2021.

See also

Seaweed farming

From the Baltic to the North Sea: Expanding WIN@sea Brings Seaweed Farming Closer to Local Fishermen

After successfully testing multi-use offshore practices at Danish Kriegers Flak in the Baltic Sea, Vattenfall and its project partners are now bringing the pioneering WIN@sea project to the ...

Read the full article
Construction work at Bruzaholm wind farm in Sweden

Teaming up for net zero: collaboration cuts carbon at Bruzaholm wind farm

When Swedish Bruzaholm wind farm is completed this autumn it will not only produce fossil free power. It will also be a shining example of how partnering can spur innovative ideas.

Read the full article

Intelligent drones increase offshore wind efficiency

Artificial intelligence combined with drones offers significant advantages for offshore wind. Advanced AI technologies not only enhance safety and efficiency of offshore activities but also ...

Read the full article