Installing first turbine at Kriegers Flak

First turbine at Kriegers Flak offshore wind farm in place

The first turbine at the Kriegers Flak offshore wind farm is in place and will deliver the first fossil-free electricity shortly. It will be the largest offshore wind farm in Denmark.

On 27 January, the tower, nacelle and blades were installed for the first turbine at the Kriegers Flak offshore wind farm in the Baltic Sea. A process that normally takes about 14 hours.

"We are proud that the first of many turbines at Kriegers Flak is now in place and ready to produce electricity. We expect that households and industry one of the coming days will receive the first fossil-free electricity from the turbine. It is an important milestone in the project, it is happening on schedule and it is fantastic to see the offshore wind farm take shape,” says Jacob Nørgaard Andersen, Country Manager at Vattenfall Denmark.

The installation follows the granting last week by the Danish Energy Agency of the license to produce electricity. Despite the restrictions caused by the COVID-19 pandemic, the construction of Kriegers Flak is generally proceeding according to plan and scheduled to be fully operational by the end of 2021, at the latest.

“Kriegers Flak makes a significant contribution in the Nordic region to our goal of enabling fossil-free living. It is a unique project integrating offshore wind production and interconnectivity between two countries – Denmark and Germany. And at the same time, it signals that the exploitation of the Baltic Sea's huge potential for offshore wind is now gaining momentum,” says Catrin Jung, Head of Offshore Wind in Vattenfall.

Compared to 2019, Kriegers Flak will increase the Danish production of wind energy by 16 per cent or enough to cover the annual electricity consumption of approximately 600,000 Danish households.

The individual parts of the turbines are assembled at Port of Roenne on the Danish island of Bornholm. Afterwards they are shipped in sets of four to the construction site at sea. The 72 turbines are produced by Siemens Gamesa Renewable Energy and will be commissioned on an ongoing basis as they are installed.

Vattenfall is Denmark's largest developer of offshore wind and is, in addition to Kriegers Flak, also building two offshore wind farms off Jutland's west coast.

Facts about Kriegers Flak

  • Kriegers Flak will have a production capacity of around 600 MW.
  • Approximately 600,000 Danish households can have their annual electricity consumption covered by the offshore wind farm.
  • Each of the 72 wind turbines is 188 metres tall, and each foundation weighs up to 800 tonnes.
  • The offshore wind farm is located in the Baltic Sea, 15-40 kilometres off the Danish coast.
  • The site covers an area of 132 km2 and has approximately 170 kilometres of subsea cables.
  • The farm is expected to be fully operational by the end of 2021.

See also

Flying bat

Are bats and wind turbines a viable cocktail at sea?

Understanding the big picture when it comes to the movement of bats over the sea is important background knowledge. It will help wind farm operators to mitigate the risk of collisions betwee...

Read the full article

Restoring peatland: From carbon leak to biodiverse carbon sink

When Vattenfall planned the largest onshore wind farm in England and Wales, Pen y Cymoedd, it also took on the restoration of up to around 1,500 hectares of blanket bog and other peatland ha...

Read the full article

Vattenfall and BASF partner with Vestas for low-emission steel wind turbines in Germany

Vattenfall and BASF have signed supply and service contracts with Vestas for 15 MW offshore wind turbines in the Nordlicht offshore wind park in Germany.

Read the full article