Construction begins on Horns Rev 3

Construction work is set to begin on Denmark's largest offshore wind farm, Horns Rev 3, in October. The project will kick off when Vattenfall installs the first of a total of 49 foundations in the North Sea. When the offshore wind farm is complete, it will provide enough power to satisfy the annual electricity consumption of 425,000 Danish households.

It is the first time in five years that an offshore wind farm will be built in Denmark.

"Horns Rev 3 is the first of three offshore farms that Vattenfall will construct in Denmark in the coming years. These wind farms will, in the highest degree, contribute to our strategy to have a fossil free energy production within one generation ," says Gunnar Groebler, head of Vattenfall´s Wind Business.

The foundations consist of 40-50-metre 'monopiles' made of steel, with a diameter of 6.5 metres. The monopiles are driven about 30 metres into the seabed and will support MHI Vestas' 8.3 MW wind turbines that are presently some of the world's most powerful turbines.

At the beginning of October, the first four monopiles were loaded onto a special vessel, the Innovation, in the Netherlands and driven into the seabed. The next four monopiles will then be loaded in the Danish Esbjerg Harbour in mid-October.

The construction work will take place in an 88 square kilometers area in the North Sea, at least 34 km off the west coast of the Danish Jutland Peninsula.

Before the construction could begin, seabed preparations had to be carried out, including a geological survey and a subsequent detonation of old naval mines. Due to noise concerns, a support vessel is being used to place an air bubble installation on the seabed around the construction site. The installation creates a sound-absorbing, double layer of air bubbles that protect marine mammals in the area.

In addition to Horns Rev 3, Vattenfall will construct the Danish Kriegers Flak and Vesterhav South and North wind farms in the years ahead.

Monopiles being loaded on vessel

Facts about Horns Rev 3:

  • The wind farm will consist of 49 turbines able to meet the annual electricity consumption of some 425,000 Danish households
  • The foundation consists of 40-50-metre-long 'monopiles', which have a diameter of 6.5 metres and weigh up to 610 tonnes
  • The 8.3 MW turbines are manufactured by MHI Vestas and are today one of the world's most powerful wind turbines
  • The turbines are 187 metres high and have a rotor diameter of 164 metres
  • Vattenfall won the contract for the construction of Horns Rev 3 in 2015
  • The wind farm has a total capacity of 406 MW

For more information, contact:
Vattenfall Press Office, +46 8 739 50 10, press@vattenfall.com

See also

Transition pieces for wind turbines. Photo: CS Wind.

First components for Nordlicht I completed ahead of schedule

The Nordlicht cluster has reached an important milestone before offshore construction is set to begin later this year: the first monopiles and transition pieces for Nordlicht I have been suc...

Read the full article
A remotely operated vessel.

World War II sea mines removed from wind farm site

Sometimes the path to clean energy starts with a look into the past. Last year, the Nordlicht project's geoscience team completed a special campaign: to remove mines from the Second World Wa...

Read the full article
Drone view of Prinses Ariane wind farm on a winter's day.

Flexibility: wind power increasingly important for a stable electricity system

Technological developments are challenging old perceptions of wind power generation. Today, wind power is becoming increasingly important in delivering ancillary services that stabilise the ...

Read the full article