Arial photo of the Princess Ariane Wind Farm wind farm in the Netherlands

Vattenfall opens Princess Ariane Wind Farm, the largest Dutch onshore wind farm

Today Vattenfall has opened the largest Dutch onshore wind farm. The former Wieringermeer wind farm was officially renamed Princess Ariane Wind Farm during an opening ceremony. It consists of 82 wind turbines and will generate renewable electricity equalling the demand of approximately 370,000 households.

“Princess Ariane Wind Farm is a light house project for us in the Netherlands for many reasons. It is another proof-point in our mission to enable fossil-free living within one generation. Furthermore, the large size also fits perfectly into our strategy of profitable growth in Europe and it underlines our successful path to re-power wind farms were possible.”, says Gunnar Groebler, Senior Vice President and Head of Vattenfall’s Business Area Wind.

Ten years of preparations and three years of construction preceded the opening of the wind farm. The turbines were built in ‘line configurations’, so they fit well into the landscape of the Wieringermeer. The total capacity of the 82 wind turbines adds up to 301MW.

What is also unique for this wind farm is that four of the wind turbines have been built in the Robbenoord woods. Thanks to the good collaboration with Staatsbosbeheer (Dutch Governmental Nature Reserve Management Agency), it is the first time in the Netherlands that wind turbines have been placed in the woods.

“The cooperation with the Dutch authorities, the municipality of Hollands Kroon and the people living in the area was exceptional and a role model for further projects, for which I would like to thank them. I would also like to thank our team for all the dedication and excellent work, that went into the Princes Ariane Wind Farm to make it such a success.”, says Gunnar Groebler.

Facts & Figures Princess Ariane Wind Farm:

  • Princess Ariane is the largest onshore wind farm in the Netherlands. The total capacity of the 82 wind turbines adds up to 301 MW and will generate renewable electricity equalling the demand of approximately 370,000 households.
  • Construction started in 2018.
  • The tip height of Vattenfall's wind turbines is 177 metres.
  • Turbine type: Nordex N117 / 3.6 MW.                                                            

For more information, please contact:
Vattenfall press office +46-8-739 50 10

See also

Finland’s first commercial-scale offshore wind farm underway

The work is already in full swing in Korsnäs off the west coast of Finland where one of the most significant industrial projects in the country is in progress. To achieve carbon neutral...

Read the full article

Hybrid technology boosts wind and solar

Increasingly weather-dependent electricity production makes grid operation more complex. A plant in Hjuleberg, Sweden, is using a solution based on new smart technology, combining wind power...

Read the full article

The energy transition: why balance matters and how to keep it

To achieve the goals of the green transition, the EU’s energy system needs to be twice as flexible by 2030 as it was in 2023. Doable? Very much so! THE EDIT explains how this can be do...

Read the full article