Today Vattenfall has opened the largest Dutch onshore wind farm. The former Wieringermeer wind farm was officially renamed Princess Ariane Wind Farm during an opening ceremony. It consists of 82 wind turbines and will generate renewable electricity equalling the demand of approximately 370,000 households.

“Princess Ariane Wind Farm is a light house project for us in the Netherlands for many reasons. It is another proof-point in our mission to enable fossil-free living within one generation. Furthermore, the large size also fits perfectly into our strategy of profitable growth in Europe and it underlines our successful path to re-power wind farms were possible.”, says Gunnar Groebler, Senior Vice President and Head of Vattenfall’s Business Area Wind.

Ten years of preparations and three years of construction preceded the opening of the wind farm. The turbines were built in ‘line configurations’, so they fit well into the landscape of the Wieringermeer. The total capacity of the 82 wind turbines adds up to 301MW.

What is also unique for this wind farm is that four of the wind turbines have been built in the Robbenoord woods. Thanks to the good collaboration with Staatsbosbeheer (Dutch Governmental Nature Reserve Management Agency), it is the first time in the Netherlands that wind turbines have been placed in the woods.

“The cooperation with the Dutch authorities, the municipality of Hollands Kroon and the people living in the area was exceptional and a role model for further projects, for which I would like to thank them. I would also like to thank our team for all the dedication and excellent work, that went into the Princes Ariane Wind Farm to make it such a success.”, says Gunnar Groebler.

Facts & Figures Princess Ariane Wind Farm:

  • Princess Ariane is the largest onshore wind farm in the Netherlands. The total capacity of the 82 wind turbines adds up to 301MW and will generate renewable electricity equalling the demand of approximately 370,000 households.
  • Construction started in 2018.
  • The tip height of Vattenfall's wind turbines is 177 metres.
  • Turbine type: Nordex N117 / 3.6 Mw                                                            
 

For more information, please contact:

Vattenfall press office +46-8-739 50 1

See also

Installing first turbine at Kriegers Flak

First turbine at Kriegers Flak offshore wind farm in place

The first turbine at the Kriegers Flak offshore wind farm is in place and will deliver the first fossil-free electricity shortly. It will be the largest offshore wind farm in Denmark.

[Missing text '/newslistpagetemplate/NewsItemPage' for 'English']
The Markbygden Phase II North wind farm in Sweden

Vattenfall sign agreement for balancing services and market access for ‘Markbygden Phase II North’ wind farm

Vattenfall will for a period of several years provide balancing services and market access for the ‘Markbygden Phase II North’ (“Markbygden”) wind farm located in the municipality of Piteå i...

Read the full article
Sea waves

The Danish Energy Agency grant permits for Vesterhav Syd and Nord

On Monday 14 December, the Danish Energy Agency gave permission for the construction work on the offshore wind farms Vesterhav Syd and Nord to begin. The Danish Energy Agency's decision cons...

[Missing text '/newslistpagetemplate/NewsItemPage' for 'English']