Grönhult wind power park - rising of power plant

The first wind turbine is now being erected at Grönhult wind farm, where a total of twelve 5.6 MW wind turbines from Vestas will be installed.

gronhult5.jpg

In May 2021, construction of the wind farm began. The work began with the construction of roads and then parking spaces, foundations and the internal electricity network for the wind farm, which is located in Tranemo and Gislaved's municipalities. The park, which has a total installed capacity of 67.2 MW, will be put into operation at the end of the year.

The wind turbines are transported by special vehicles from the ports in Falkenberg and Karlshamn. The vehicles are very large and long, so in order to minimise traffic disruptions the transports take place at night.

"We are delighted to have reached this crucial milestone in the construction of the Grönhult wind farm. The entire project team have worked tirelessly, alongside our contract partners to reach this point. We are confident that with the weather on our side we will be able to continue with the installation of all 12 turbines over the summer in line with our programme," says Bryan Wright, Portfolio Director at Vattenfall.

gronhult4.jpg

In February 2021, Grönhult was sold to the investment company TRIG, The Renewables Infrastructure Group Limited. Vattenfall Vindkraft is building the park and will be responsible for the management of the wind farm during operation which means, among other things, ensuring that permits are complied with and maintaining contacts with landowners and authorities. The twelve wind turbines will be able to supply about 40,000 homes with renewable household electricity annually.

For more info

Facts

  • Location, Gislaved and Tranemo municipalities, Jönköping and Västra Götaland counties
  • Twelve wind turbines, V162-5.6 MW
  • Total installed capacity, 67.2 MW
  • Total height, 200 meters
  • Rotor diameter, 162 meters
  • Potential annual production 210 GWh, which corresponds to the annual consumption of household electricity for approximately 40,000 customers.
  • Legally enforced permit, May 2019
  • Commissioning, end of 2022
  • Regional network owner, Vattenfall Eldistribution

See also

Flying bat

Are bats and wind turbines a viable cocktail at sea?

Understanding the big picture when it comes to the movement of bats over the sea is important background knowledge. It will help wind farm operators to mitigate the risk of collisions betwee...

Read the full article

Restoring peatland: From carbon leak to biodiverse carbon sink

When Vattenfall planned the largest onshore wind farm in England and Wales, Pen y Cymoedd, it also took on the restoration of up to around 1,500 hectares of blanket bog and other peatland ha...

Read the full article

Vattenfall and BASF partner with Vestas for low-emission steel wind turbines in Germany

Vattenfall and BASF have signed supply and service contracts with Vestas for 15 MW offshore wind turbines in the Nordlicht offshore wind park in Germany.

Read the full article