Final turbine successfully installed for EOWDC

While world’s fastest installation of suction bucket jacket foundation could mark fourth offshore wind industry first for the Scottish project

View a time-lapse video of one of the turbine installations below or click here to view it in Youtube.

The final turbine for the European Offshore Wind Deployment Centre (EOWDC) has been successfully installed with the project recording what is believed to be the world’s fastest installation of a gigantic, game-changing suction bucket jacket foundation.

Saturday’s (Saturday, May 26) turbine installation comes just nine weeks after the first foundation for the 11-turbine EOWDC scheme off Aberdeen Bay was deployed in the North Sea.

Adam Ezzamel, EOWDC project director at Vattenfall, said: “This is a magnificent offshore engineering feat for a project that involves industry-first technology and innovative approaches to the design and construction. Throughout construction, the project team and our contractors have encountered, tackled and resolved a number of challenges. The erection of the final turbine is a significant milestone, and with the completion of array cable installation, we now move on to the final commissioning phase of the wind farm prior to first power later this summer.

“One of our 1,800 tonne suction bucket jacket foundation was installed in what we believe is a world record of two hours and 40 minutes from the time the installation vessel entered the offshore site until deployment was complete. What makes this even more significant is that the EOWDC is the first offshore wind project to deploy this kind of foundation at commercial scale while it’s also the first to pair them with the world’s most powerful turbines.

“Full credit goes to the expertise of our project team and contractors who have worked collaboratively and vigorously to achieve this remarkable milestone in such a short timescale. As a flagship project for the North-east, the EOWDC helps underline the region’s status as Europe’s energy capital and reinforces Vattenfall’s vision to be fossil free within one generation.”

MHI Vestas Chief Operations Officer, Flemming Ougaard, said: “We’re excited to see that the last turbine has been safely installed at Aberdeen Bay with our partner, Vattenfall. With clean power set to soon flow to the national grid from all 11 turbines, we very much look forward to operations and service at the new offshore wind park.”

The ground-breaking 93.2MW EOWDC, which is scheduled to generate first power in the summer, will produce the equivalent of more than 70% of Aberdeen’s domestic electricity demand and annually displace 134,128 tonnes of CO2.

It features nine 8.4MW turbines along with two 8.8MW models which both represent an industry first in that they are the first of this power capability to be deployed commercially in the offshore wind industry. As a result, all turbines will enable the EOWDC to generate more clean energy.

See also

New deal signed for offshore wind innovators to continue driving forward solutions in real-world conditions

Vattenfall and the Offshore Renewable Energy (ORE) Catapult have signed a three-year extension on their testing and demonstration collaboration at Aberdeen Offshore Wind Farm.

Read the full article

Equivalent of 5000 homes served by Vattenfall’s Bristol Heat Network

As part of Bristol City Leap, Vattenfall Heat UK is now serving the equivalent of 5000 homes with heating and hot water via the Bristol Heat Network.

Read the full article

Vattenfall and RWE conclude sale of Norfolk Offshore Wind Zone

Vattenfall has today completed the sale of the Norfolk Offshore Wind Zone to RWE. The agreed purchase price corresponds to an enterprise value of £963 million.

Read the full article