South Kyle Wind Farm, one of the first foundations

50th and final wind turbine foundation poured at South Kyle Wind Farm

  • Construction passes significant milestone as final turbine foundation poured
  • Construction is currently eight months ahead of schedule
  • Work started in June 2020 with site due to be operational by early 2023

Construction has reached a significant milestone eight months ahead of schedule, as the concrete pour on the final and fiftieth turbine foundation was completed at South Kyle Wind Farm, Vattenfall’s 240MW project in south west Scotland.

RJ McLeod based in Glasgow, is leading the operation along with Foundation Solutions HV a specialist foundation contractor based in East Ayrshire.

The completion of the final foundation marks a change in the emphasis of the works onsite, which now turn to the electrical works.  Over the coming months 72km of 33kV cable will be laid and work will continue at the new South Kyle substation and on the grid connection. 

Civil works will now focus on finishing the foundations and environmental restoration of the areas where rock has been extracted for use at the site as well as preparing the access route and site for wind turbine deliveries which are scheduled to commence in Spring 2022.

South Kyle Wind Farm is set to be fully commissioned and producing electricity from Spring 2023. Once energised it will be generating enough electricity to meet the equivalent demand of approximately 170,000 UK homes1 annually, more than all of the homes in East Ayrshire and Dumfries & Galloway combined.

Paul Nickless, Vattenfall’s Project Director for South Kyle, said:

“Reaching this important milestone eight months ahead of schedule is a great achievement and the result of lots of hard work from all of our contractors including RJ McLeod and Foundation Solutions HV, who are based just a few miles from South Kyle. 

“What they have managed to achieve, despite recent materials and driver shortages as well as the ongoing pandemic, is extremely impressive.

“It’s exciting to think that by 2023, South Kyle Wind Farm will be generating fossil-fuel free power and making a significant contribution to Scotland’s net zero goals.”

 

Notes 

1 https://www.renewableuk.com/page/UKWEDSearch

Number of homes: East Ayrshire: Local Housing Strategy 2019-2024 (east-ayrshire.gov.uk)

Dumfries and Galloway: Dumfries and Galloway Council Area Profile (nrscotland.gov.uk)

See also

Muir Mhòr floating offshore wind farm project passes planning milestone

Our joint venture with Fred. Olsen Seawind has passed another major milestone with the approval of our onshore consent application. 

Read the full article

Vattenfall IDNO partners with Netcontrol to improve efficiency of networks

Vattenfall IDNO has entered a strategic partnership with Netcontrol to roll out advanced automation solutions across its UK electricity networks.

Read the full article

Vattenfall Celebrates 10 Years of Clashindarroch Wind Farm with “10 Years in 10 Stories” Community Campaign

Vattenfall is celebrating a decade of renewable energy generation and community investment through its Clashindarroch Wind Farm.

Read the full article